Easy carried out one of the phases of the renovation of the historic BM&F building, today B3, in downtown São Paulo, around 2011. The project renovated part of the building’s floors, with the exchange fully operating and all the restricted logistics of the downtown area. Delivery was Turnkey.
The challenge: working in the exchange building while the exchange is open
The building kept operating throughout the project. The renovation had to move forward in parallel with operations, inside an occupied building.
The location added another layer. In downtown São Paulo, the entry of materials, removal of debris and movement of crews depend on limited hours and access, and the project planning had to start from these restrictions.
Historic building renovation in São Paulo
The BM&F building is a historic building, and the architectural design set an aesthetic standard that respected the original architecture and the period of construction. Easy’s execution followed this standard in every space of its phase.
What Easy built
The project took place after the end of open-outcry trading, when trading became electronic. As a result, the renovated floors no longer housed trading floor areas and received a different program:
- office areas;
- meeting rooms.
Schedule and method: one phase of a larger project
The building’s renovation was divided into phases. The client hired the architectural design directly, and Easy was the contractor chosen to carry out one of these phases, under a construction contract.
Working within a larger project means delivering to the same standard as the other phases and at the pace set by the client. Easy’s phase was carried out following the design and the building’s operating conditions.
Result
BM&F received the renovated floors, with offices and meeting rooms adapted to the exchange’s new routine and aligned with the building’s historic architecture. See other projects in the Corporate segment.
Frequently asked questions
- What did Easy carry out in the BM&F building?
- One of the phases of the renovation of the exchange’s historic building, in downtown São Paulo. Easy renovated part of the floors, converted into offices and meeting rooms.
- Did the exchange keep operating during the project?
- Yes. The renovation was carried out with BM&F in operation, which required logistics planning compatible with the building’s operation and the restrictions of the city center.
- How was Easy hired?
- Under a construction contract. The architectural design was hired directly by the client, and Easy was chosen to carry out one of the project’s phases. Delivery was Turnkey.
- How do you renovate a historic building while keeping its identity?
- By following the aesthetic standard defined in the design. At BM&F, execution respected the building’s original architecture and the period in which it was built.