Belas Artes

Belas Artes

Client
Belas Artes
Location
Vila Mariana, São Paulo, SP

Easy carried out the main project for Belas Artes on the Vila Mariana campus, in São Paulo: a children’s library, a computer lab and classrooms, over an intervention area of more than 2,000 sqm. The work was done during the school break, Turnkey, and delivered in 65 days, in time for the start of the 2013 school year.

What was the scope of the Belas Artes project?

Easy carried out the main project on the Vila Mariana campus, with more than 2,000 sqm of intervention:

  • children’s library;
  • computer lab;
  • classrooms.

What was the main challenge?

The opening date. School renovations have a deadline that does not move: classes start on a fixed date. Belas Artes set the calendar, and Easy concentrated execution in the break period, delivering the spaces ready for the start of the school year.

What was the contracting model?

The design was developed by Belas Artes’ own architecture school and handed to contractors in the bid. Easy won and carried out the complete project, with Turnkey delivery: the spaces ready, for a fixed price.

What was the result of the project?

The spaces were delivered within the 65-day deadline, meeting the institution’s expectations.

The relationship began at the end of 2012, with the renovation of classrooms. After the main project came the IT room and the open-course classrooms, each with its own proposal and approval. Belas Artes is a repeat client of Easy.

See other projects in the Educational segment.

Frequently asked questions

Does Easy carry out school projects during the break?
Yes. At Belas Artes, the project was carried out during the school break and delivered in 65 days, in time for the start of the 2013 school year.
What was the project area?
More than 2,000 sqm of intervention.
Which spaces did Easy deliver for Belas Artes?
The children’s library, the computer lab and classrooms. In other requests on the same campus, Easy also built an IT room and open-course classrooms.
What was the project's contracting model?
Turnkey construction. Belas Artes provided the designs, from the institution’s own interior architecture department, and Easy won the bid to carry out everything with complete delivery.
Was the children's library part of the main project?
Yes. The children’s library and the computer lab were part of the main package, delivered in 65 days during the break.

Belas Artes

Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring
Belas Artes children's library in Vila Mariana, with bamboo-slat wall cladding and wood-look vinyl flooring