Change plan: do you know what that is?
· 3 min
The Change Plan gives the client full control over completing the corporate build-out and settling employees into the new space.

The company Cia&CIA decided it would be best to do a fit-out of its headquarters — after all, it was growing and needed a more upscale space for its office. All the work of choosing the new address was done. A specialized corporate architecture firm was hired. The design was ready. Everyone liked it. The corporate build-out happened within the planned schedule and budget. Everything went well. Now only the “easiest” part of the process remained: the move.
Although the client had been warned about the importance of carrying out a change plan, Cia&CIA’s administrative manager decided he could handle this responsibility himself. There was no need for “big plans.” No one was too worried, after all the company had “only” 40 employees. All it took was hiring a moving company that would guarantee everything would be delivered as promised — that is, at the agreed place and date.
That’s when things started to get complicated. On the Monday following the move, our manager’s life had turned into a nightmare. Several computers were mixed up, personal belongings had gone missing, much of the equipment hadn’t been reassembled, clients hadn’t been informed of the extension number changes, and employees didn’t know where the support services (banks, restaurants, buses, subway) were in the new area. With every new problem that came up, reality became clearer. The company was paralyzed. The puzzle hadn’t been put back together correctly. The last piece of the process was missing: the Change Plan. But what exactly is a real change plan?
The goal of the Change Plan is to provide a management system that gives the client perfect and complete control over the process of finishing a corporate build-out, starting operations at the new site, and settling in its staff with full emotional and productive capacity.
According to Easy’s managers, the two fundamental principles that must always be followed in this phase are:
- The physical moving process and its consequences for the company’s productivity;
- The psychological impact of the move on employees and its consequences for the success of the venture and its potential.
Below are the 12 Commandments of a Good Move. They are the foundation of the services Easy develops to make sure a headquarters move during a fit-out is successful.
The 12 Commandments of a Good Move
- Preparation and follow-up of a detailed Change Master Plan – CMP;
- Preparation, integration and systematic follow-up of a single macro-activity schedule, covering all finishing services, availability of systems and equipment, and department organization;
- Development of specific forms to support the CMP;
- Registration and integration of the Service Provider companies hired by the Client Company;
- Development of a complete Training Program for the employees involved in this phase;
- Preparation of requests for proposals and bidding, complete analysis, and identification of the most suitable cost opportunities and systems for the Client Company’s profile during the hiring phase for external and internal transportation companies;
- Organization of discussions with the departments designated by the company, aiming to minimize negative impacts and maximize the resulting positive impacts;
- Follow-up and updating of communication channels to employees;
- Control of basic supplies to support operations at the new headquarters during the process;
- Coordination of a Help Desk to support the moving system;
- Oversight of the installation of special equipment, such as generators, UPS units, standard power outlets, alternative power, voice and data at workstations, structured cabling installation, furniture assembly, partition assembly and everything else necessary for occupying the building;
- Follow-up with the moving company at every stage of the move.